COUNTY OF PASSAIC ROAD RESURFACING PROGRAM, 2023
Bid Location
Category
Bid Date
1 | CLEARING SITE | LS | 1 | $267,000.00 | $267,000.00 | $295,000.00 | $295,000.00 | $194,422.25 | $194,422.25 | $350,000.00 | $350,000.00 | $200,000.00 | $200,000.00 | $1,265,000.00 | $1,265,000.00 |
2 | Breakaway Barricade | UNIT | 100 | $40.00 | $4,000.00 | $50.00 | $5,000.00 | $1.00 | $100.00 | $60.00 | $6,000.00 | $65.00 | $6,500.00 | $0.01 | $1.00 |
3 | Drum | UNIT | 200 | $20.00 | $4,000.00 | $50.00 | $10,000.00 | $1.00 | $200.00 | $50.00 | $10,000.00 | $50.00 | $10,000.00 | $0.01 | $2.00 |
4 | Traffic Cone | UNIT | 200 | $13.20 | $2,640.00 | $20.00 | $4,000.00 | $1.00 | $200.00 | $17.00 | $3,400.00 | $15.00 | $3,000.00 | $0.01 | $2.00 |
5 | Construction Signs | SF | 600 | $15.00 | $9,000.00 | $10.00 | $6,000.00 | $1.00 | $600.00 | $12.00 | $7,200.00 | $15.00 | $9,000.00 | $3.00 | $1,800.00 |
6 | ADVANCE DATE OF CONSTRUCTION SIGN | SF | 720 | $15.00 | $10,800.00 | $10.00 | $7,200.00 | $25.00 | $18,000.00 | $17.00 | $12,240.00 | $15.00 | $10,800.00 | $1.75 | $1,260.00 |
7 | Traffic Director, Flagger (If & Where Directed) | HOURS | 2,300 | $83.30 | $191,590.00 | $83.28 | $191,544.00 | $83.28 | $191,544.00 | $83.28 | $191,544.00 | $83.28 | $191,544.00 | $83.28 | $191,544.00 |
8 | TRAFFIC SAFETY SERVICES | ALLOWANCE | 1 | $50,000.00 | $50,000.00 | $50,000.00 | $50,000.00 | $50,000.00 | $50,000.00 | $50,000.00 | $50,000.00 | $50,000.00 | $50,000.00 | $50,000.00 | $50,000.00 |
9 | Asphalt Price Adjustment | DOLLAR | 50,000 | $1.00 | $50,000.00 | $1.00 | $50,000.00 | $1.00 | $50,000.00 | $1.00 | $50,000.00 | $1.00 | $50,000.00 | $1.00 | $50,000.00 |
10 | EXCAVATION, TEST PIT (IF & WHERE DIRECTED) | CY | 60 | $100.00 | $6,000.00 | $0.01 | $0.60 | $1.00 | $60.00 | $20.00 | $1,200.00 | $20.00 | $1,200.00 | $100.00 | $6,000.00 |
12 | HMA Milling, 3" or Less | SY | 180,890 | $4.12 | $745,266.80 | $4.36 | $788,680.40 | $3.85 | $696,426.50 | $4.50 | $814,005.00 | $4.50 | $814,005.00 | $4.20 | $759,738.00 |
13 | HOT MIX ASPHALT BASE REPAIR (IF & WHERE DIRECTED) | SY | 2,520 | $20.50 | $51,660.00 | $0.01 | $25.20 | $35.00 | $88,200.00 | $31.00 | $78,120.00 | $35.00 | $88,200.00 | $16.00 | $40,320.00 |
15 | HOT MIX ASPHALT 9.5M64 SURFACE COURSE, 2" THICK | TON | 21,180 | $93.04 | $1,970,587.20 | $106.00 | $2,245,080.00 | $101.00 | $2,139,180.00 | $93.00 | $1,969,740.00 | $90.00 | $1,906,200.00 | $90.50 | $1,916,790.00 |
16 | HOT MIX ASPHALT DRIVEWAY, 4" THICK | SY | 25 | $47.80 | $1,195.00 | $109.00 | $2,725.00 | $140.00 | $3,500.00 | $65.00 | $1,625.00 | $200.00 | $5,000.00 | $50.00 | $1,250.00 |
18 | 1/2" CRUSHED STONE | CY | 200 | $50.00 | $10,000.00 | $205.00 | $41,000.00 | $60.00 | $12,000.00 | $50.00 | $10,000.00 | $55.00 | $11,000.00 | $36.15 | $7,230.00 |
19 | RIPRAP STONE CHANNEL PROTECTION, 12" THICK (D50=18") | SY | 20 | $100.00 | $2,000.00 | $270.00 | $5,400.00 | $100.00 | $2,000.00 | $75.00 | $1,500.00 | $100.00 | $2,000.00 | $80.00 | $1,600.00 |
20 | RECONSTRUCTED INLET. USING NEW CASTING | UNIT | 170 | $1,500.00 | $255,000.00 | $1.29 | $219.30 | $1,000.00 | $170,000.00 | $1,600.00 | $272,000.00 | $2,000.00 | $340,000.00 | $2,625.00 | $446,250.00 |
21 | SET INLET TYPE A, CASTING | UNIT | 2 | $765.00 | $1,530.00 | $1,209.00 | $2,418.00 | $1,200.00 | $2,400.00 | $1,000.00 | $2,000.00 | $1,500.00 | $3,000.00 | $2,835.00 | $5,670.00 |
22 | SET INLET TYPE B, CASTING | UNIT | 2 | $765.00 | $1,530.00 | $1.29 | $2.58 | $1,500.00 | $3,000.00 | $1,400.00 | $2,800.00 | $1,500.00 | $3,000.00 | $3,150.00 | $6,300.00 |
23 | Cleaning Drainage Structure | UNIT | 1 | $400.00 | $400.00 | $1,015.00 | $1,015.00 | $1,700.00 | $1,700.00 | $1,500.00 | $1,500.00 | $5,000.00 | $5,000.00 | $3,465.00 | $3,465.00 |
24 | MANHOLE 4' DIAMETER | UNIT | 2 | $5,500.00 | $11,000.00 | $1.29 | $2.58 | $5,000.00 | $10,000.00 | $5,000.00 | $10,000.00 | $5,000.00 | $10,000.00 | $2,520.00 | $5,040.00 |
25 | Inlet, Type A (If & Where Directed) | UNIT | 7 | $4,000.00 | $28,000.00 | $1.29 | $9.03 | $4,000.00 | $28,000.00 | $4,500.00 | $31,500.00 | $5,000.00 | $35,000.00 | $2,835.00 | $19,845.00 |
26 | Inlet, Type B (If & Where Directed) | UNIT | 7 | $4,430.00 | $31,010.00 | $1.29 | $9.03 | $4,000.00 | $28,000.00 | $5,500.00 | $38,500.00 | $5,000.00 | $35,000.00 | $3,150.00 | $22,050.00 |
27 | INLET. TYPE D (IF & WHERE DIRECTED) | UNIT | 5 | $3,900.00 | $19,500.00 | $1.29 | $6.45 | $4,000.00 | $20,000.00 | $5,500.00 | $27,500.00 | $5,000.00 | $25,000.00 | $3,360.00 | $16,800.00 |
28 | INLET, TYPE E (IF & WHERE DIRECTED) | UNIT | 5 | $5,000.00 | $25,000.00 | $1.29 | $6.45 | $4,000.00 | $20,000.00 | $6,000.00 | $30,000.00 | $5,000.00 | $25,000.00 | $3,465.00 | $17,325.00 |
29 | Reset Existing Casting | UNIT | 220 | $171.00 | $37,620.00 | $1.29 | $283.80 | $200.00 | $44,000.00 | $225.00 | $49,500.00 | $350.00 | $77,000.00 | $100.00 | $22,000.00 |
30 | 12" DUCTILE IRON PIPE, CLASS 56 | LF | 130 | $172.00 | $22,360.00 | $293.00 | $38,090.00 | $250.00 | $32,500.00 | $187.00 | $24,310.00 | $300.00 | $39,000.00 | $336.00 | $43,680.00 |
31 | SET NEW MANHOLE CASTING, SUPPLIED BY OTHERS | UNIT | 5 | $900.00 | $4,500.00 | $605.00 | $3,025.00 | $550.00 | $2,750.00 | $225.00 | $1,125.00 | $450.00 | $2,250.00 | $262.50 | $1,312.50 |
32 | Bicycle Safe Grate (If Where Directed) | UNIT | 5 | $382.00 | $1,910.00 | $905.00 | $4,525.00 | $600.00 | $3,000.00 | $400.00 | $2,000.00 | $500.00 | $2,500.00 | $400.00 | $2,000.00 |
33 | CURB PIECE, TYPE N-ECO (IF & WHERE DIRECTED) | UNIT | 5 | $382.00 | $1,910.00 | $905.00 | $4,525.00 | $700.00 | $3,500.00 | $350.00 | $1,750.00 | $500.00 | $2,500.00 | $450.00 | $2,250.00 |
34 | Concrete Sidewalk 4" thick | SY | 1,450 | $91.05 | $132,022.50 | $91.20 | $132,240.00 | $85.00 | $123,250.00 | $95.00 | $137,750.00 | $100.00 | $145,000.00 | $112.35 | $162,907.50 |
35 | DETECTABLE WARNING SURFACE, TRUNCATED DOMES, CAST IN PLACE | SY | 90 | $255.00 | $22,950.00 | $185.00 | $16,650.00 | $300.00 | $27,000.00 | $200.00 | $18,000.00 | $300.00 | $27,000.00 | $336.00 | $30,240.00 |
36 | 9" x 18" Concrete Vertical Curb | LF | 1,990 | $39.00 | $77,610.00 | $45.00 | $89,550.00 | $70.00 | $139,300.00 | $46.00 | $91,540.00 | $50.00 | $99,500.00 | $81.90 | $162,981.00 |
37 | Bollard | UNIT | 4 | $1,000.00 | $4,000.00 | $1,280.00 | $5,120.00 | $900.00 | $3,600.00 | $1,200.00 | $4,800.00 | $2,000.00 | $8,000.00 | $550.00 | $2,200.00 |
38 | Set Manhole Casting | UNIT | 5 | $900.00 | $4,500.00 | $905.00 | $4,525.00 | $1,000.00 | $5,000.00 | $800.00 | $4,000.00 | $500.00 | $2,500.00 | $250.00 | $1,250.00 |
39 | 15" Reinforced Concrete Pipe | LF | 50 | $115.00 | $5,750.00 | $157.00 | $7,850.00 | $150.00 | $7,500.00 | $113.00 | $5,650.00 | $350.00 | $17,500.00 | $247.80 | $12,390.00 |
40 | 8" DUCTILE IRON PIPE, CLASS 56 | LF | 105 | $135.00 | $14,175.00 | $200.00 | $21,000.00 | $160.00 | $16,800.00 | $156.00 | $16,380.00 | $250.00 | $26,250.00 | $231.00 | $24,255.00 |
41 | TRIMMING EXISTING TREES | UNIT | 5 | $400.00 | $2,000.00 | $220.00 | $1,100.00 | $500.00 | $2,500.00 | $700.00 | $3,500.00 | $200.00 | $1,000.00 | $350.00 | $1,750.00 |
43 | CENTERLINE RUMBLESTRIP WITH FOG SEAL | LF | 18,275 | $0.95 | $17,361.25 | $3.05 | $55,738.75 | $3.00 | $54,825.00 | $4.00 | $73,100.00 | $3.00 | $54,825.00 | $0.23 | $4,203.25 |
44 | Traffic Marking Lines, 4" | LF | 97,250 | $0.45 | $43,762.50 | $0.60 | $58,350.00 | $0.80 | $77,800.00 | $0.80 | $77,800.00 | $0.75 | $72,937.50 | $0.65 | $63,212.50 |
45 | TRAFFIC MARKING LINES, 8" | LF | 17,725 | $1.05 | $18,611.25 | $1.02 | $18,079.50 | $0.95 | $16,838.75 | $0.98 | $17,370.50 | $1.50 | $26,587.50 | $1.26 | $22,333.50 |
46 | Traffic Markings Lines, 6" | LF | 460 | $1.89 | $869.40 | $2.20 | $1,012.00 | $2.10 | $966.00 | $3.00 | $1,380.00 | $1.25 | $575.00 | $1.16 | $533.60 |
48 | TRAFFIC MARKINGS LINES, 24" | LF | 6,680 | $3.91 | $26,118.80 | $6.60 | $44,088.00 | $6.25 | $41,750.00 | $6.20 | $41,416.00 | $5.00 | $33,400.00 | $4.20 | $28,056.00 |
49 | Traffic Markings Symbols | SF | 1,245 | $8.11 | $10,096.95 | $7.15 | $8,901.75 | $7.50 | $9,337.50 | $7.50 | $9,337.50 | $5.00 | $6,225.00 | $6.25 | $7,781.25 |
50 | RPM, Bi-Directional, Amber Lens | UNIT | 460 | $36.80 | $16,928.00 | $38.45 | $17,687.00 | $37.00 | $17,020.00 | $39.00 | $17,940.00 | $40.00 | $18,400.00 | $35.70 | $16,422.00 |
51 | RPM, MONO-DIRECTIONAL, WHITE LENS | UNIT | 375 | $36.80 | $13,800.00 | $38.45 | $14,418.75 | $37.00 | $13,875.00 | $39.00 | $14,625.00 | $40.00 | $15,000.00 | $35.70 | $13,387.50 |
52 | REGULATORY AND WARNING SIGN WITH POST | SF | 675 | $45.00 | $30,375.00 | $50.50 | $34,087.50 | $37.00 | $24,975.00 | $69.00 | $46,575.00 | $40.00 | $27,000.00 | $52.50 | $35,437.50 |
53 | BICYCLE LANE MARKINGS | UNIT | 35 | $150.00 | $5,250.00 | $385.00 | $13,475.00 | $450.00 | $15,750.00 | $400.00 | $14,000.00 | $300.00 | $10,500.00 | $325.50 | $11,392.50 |
54 | RPM, MONO-DIRECTIONAL, AMBER LENS | UNIT | 140 | $36.80 | $5,152.00 | $38.45 | $5,383.00 | $37.00 | $5,180.00 | $39.00 | $5,460.00 | $40.00 | $5,600.00 | $35.70 | $4,998.00 |
55 | Topsoil Spreading, 4" Thick (If & Where Directed) | SY | 500 | $6.43 | $3,215.00 | $8.00 | $4,000.00 | $5.00 | $2,500.00 | $10.00 | $5,000.00 | $8.00 | $4,000.00 | $6.00 | $3,000.00 |
56 | FERTILIZING AND SEEDING, TYPE A-3 (IF & WHERE DIRECTED) | SY | 500 | $2.59 | $1,295.00 | $1.00 | $500.00 | $1.00 | $500.00 | $1.00 | $500.00 | $5.00 | $2,500.00 | $1.00 | $500.00 |
57 | Straw Mulching (If & Where Directed) | SY | 500 | $1.25 | $625.00 | $1.00 | $500.00 | $1.00 | $500.00 | $1.00 | $500.00 | $6.00 | $3,000.00 | $1.00 | $500.00 |
58 | Removal of Beam Guide Rail | LF | 150 | $3.00 | $450.00 | $3.30 | $495.00 | $1.00 | $150.00 | $3.00 | $450.00 | $20.00 | $3,000.00 | $1.00 | $150.00 |
59 | Tangent Guide Rail Terminal | UNIT | 27 | $4,090.00 | $110,430.00 | $4,230.00 | $114,210.00 | $4,600.00 | $124,200.00 | $4,000.00 | $108,000.00 | $4,500.00 | $121,500.00 | $4,725.00 | $127,575.00 |
60 | Beam Guide Rail Anchorage | UNIT | 6 | $2,000.00 | $12,000.00 | $1,375.00 | $8,250.00 | $2,600.00 | $15,600.00 | $1,400.00 | $8,400.00 | $2,000.00 | $12,000.00 | $2,625.00 | $15,750.00 |
61 | Beam Guide Rail | LF | 4,325 | $37.46 | $162,014.50 | $30.70 | $132,777.50 | $50.00 | $216,250.00 | $29.00 | $125,425.00 | $50.00 | $216,250.00 | $49.35 | $213,438.75 |
62 | Controlled Release Terminal | UNIT | 10 | $1,600.00 | $16,000.00 | $1,265.00 | $12,650.00 | $1,700.00 | $17,000.00 | $1,250.00 | $12,500.00 | $30,000.00 | $300,000.00 | $1,680.00 | $16,800.00 |
63 | STUMP REMOVAL | UNIT | 1 | $500.00 | $500.00 | $1,000.00 | $1,000.00 | $500.00 | $500.00 | $800.00 | $800.00 | $1,000.00 | $1,000.00 | $787.50 | $787.50 |
64 | RECONSTRUCTED MANHOLE USING NEW CASTINGS | UNIT | 25 | $900.00 | $22,500.00 | $1.29 | $32.25 | $1,200.00 | $30,000.00 | $1,000.00 | $25,000.00 | $1,500.00 | $37,500.00 | $2,500.00 | $62,500.00 |
65 | RECONSTRUCTED MANHOLE USING NEW CASTINGS SUPPLIED BY OTHERS | UNIT | 5 | $900.00 | $4,500.00 | $450.00 | $2,250.00 | $750.00 | $3,750.00 | $700.00 | $3,500.00 | $1,200.00 | $6,000.00 | $2,000.00 | $10,000.00 |
66 | BORROW TOPSOIL (IF & WHERE DIRECTED) | CY | 50 | $40.00 | $2,000.00 | $1.00 | $50.00 | $20.00 | $1,000.00 | $50.00 | $2,500.00 | $40.00 | $2,000.00 | $5.00 | $250.00 |
67 | BEAM GUIDE RAIL POST, LONG | UNIT | 50 | $90.00 | $4,500.00 | $125.00 | $6,250.00 | $90.00 | $4,500.00 | $130.00 | $6,500.00 | $200.00 | $10,000.00 | $262.50 | $13,125.00 |
68 | Beam Guide Rail Element | LF | 25 | $22.30 | $557.50 | $12.50 | $312.50 | $20.00 | $500.00 | $15.00 | $375.00 | $30.00 | $750.00 | $262.50 | $6,562.50 |
69 | Controlled Release Terminal Anchorage | UNIT | 5 | $2,200.00 | $11,000.00 | $3,075.00 | $15,375.00 | $2,500.00 | $12,500.00 | $3,000.00 | $15,000.00 | $45,000.00 | $225,000.00 | $2,625.00 | $13,125.00 |
70 | Nonvegetative Surface, Hot Mix Asphalt | SY | 4,250 | $40.00 | $170,000.00 | $0.90 | $3,825.00 | $56.00 | $238,000.00 | $57.00 | $242,250.00 | $50.00 | $212,500.00 | $15.75 | $66,937.50 |
71 | BEAM GUIDE RAIL POST (IF AND WHERE DIRECTED) | UNIT | 50 | $90.00 | $4,500.00 | $92.30 | $4,615.00 | $80.00 | $4,000.00 | $88.00 | $4,400.00 | $180.00 | $9,000.00 | $262.50 | $13,125.00 |
$4,794,428.65 | $4,612,140.92 | $5,090,000.00 | $5,212,783.00 | $5,726,499.00 | $6,076,381.85 |